In one recently commissioned building, the systems appeared to be performing well during initial startup. Cooling mode testing was completed successfully, alarms were cleared, and the building was turned over to operations. Within weeks of the seasonal change to heating, comfort complaints and equipment alarms began to surface.
The root cause was not equipment failure. It was a control sequence that had never been fully tested in heating mode. A single condition in the sequence caused the unit to lock into an unintended operating state once outdoor air temperatures dropped below a certain threshold. The issue remained hidden during summer testing and only became apparent when the building entered full heating operation.
This scenario is far more common than many owners expect. Construction schedules often compress seasonal testing, and systems are frequently turned over before all operating modes can be validated. As a result, buildings may appear stable until actual outdoor conditions expose gaps in the control sequence.
Commissioning plays a critical role in identifying these risks early, documenting limitations, and planning for follow-up testing. When issues do arise, having a clear understanding of the system intent allows teams to troubleshoot efficiently rather than reactively. In this case, once the sequence was corrected and retested, the system stabilized and performance improved immediately.
The lesson is simple: systems should not only be started but also fully tested under real-life conditions. Real performance is proven over time and across seasons.